Skip to main content
Manufacturing · Owner's representativeBécancour, QC · 2021—2024

Advanced Manufacturing Plant.

A greenfield manufacturing facility delivered to a fixed production start-up — commissioned on date, with the line coming up on plan.

Hero image · 21:8
Project · Manufacturing Plant
Client
Manufacturer (confidential)
Capital value
$540M
Duration
3 years
CREO role
Controls · Owner's rep
Status
Delivered · On time
The brief

A start-up date set by the market, not the build.

The manufacturer had committed to a production start-up date driven by customer demand — long before the greenfield site was cleared. Equipment lead times ran longer than the construction schedule, and commissioning, not concrete, sat on the critical path.

CREO was engaged as owner's representative and project controls lead: accountable for cost and schedule across the EPC and equipment vendors, and for protecting the start-up through ramp-up.

Scope of services
  • Project & cost controls
  • Owner's representation
  • Common data environment (PMIS)
  • Long-lead procurement sequencing
  • Commissioning support
  • Claims avoidance & support
Project photo · 16:7
Process equipment set during the mechanical-completion phase — sequenced against long-lead delivery dates.

The challenge

Major process equipment carried lead times measured in quarters, and a single late delivery could push commissioning past the committed start-up. Construction, vendors, and the commissioning team were each working to their own schedule.

The owner needed one integrated plan — procurement, construction, and commissioning on a single critical path, sequenced backward from the start-up date.

Our approach

  1. 01
    Sequenced the schedule from start-up backward
    Built one integrated model working back from the production date — so every procurement and construction milestone served commissioning.
  2. 02
    Tracked long-lead procurement to the critical path
    Tied every major equipment order to the schedule, flagging delivery risk before it reached the field.
  3. 03
    Integrated commissioning early
    Brought commissioning into the plan from the start, so mechanical completion handed straight into start-up without a gap.
  4. 04
    Kept the record claim-ready
    Documented every delay and change as it happened — protecting the owner across EPC and vendor contracts.
The outcome

On the line, on the date.

On time
Production start-up achieved on the committed date.
0
Commissioning delays from late procurement.
1
Integrated plan across EPC, vendors, and commissioning.
0
Claims reaching formal dispute.
On site
Photo · 4:3
Photo · 4:3
Photo · 4:3
In their words
“CREO ran the whole program back from our start-up date. Procurement, construction, and commissioning were one plan — so nothing surprised us. The line came up exactly when we promised our customers.”
Project Sponsor
Manufacturer (confidential)
Talk to us

We build
efficiency.

Montréal · Headquarters

4388 Rue Saint-Denis
Suite 200, P.O. Box 162
Montréal, Québec H2J 2L1

General inquiries

T : +1 438 788 3639
E : info@creo-solutions.ca

Hours

9.00am to 5.00pm (EST)
Monday to Friday

Advanced Manufacturing Plant · CREO Solutions